Phases 1 to 4 of the SJRQ Consolidation Project complete at State Street Bank
July 14, 2017Successful completion and handover of the 5th Floor, Phases 1 to 4 at State Street Bank, Dublin. Well done to all the team involved on this project....
Construction works get underway at the Holy Ghost Residential Home, Waterford
July 06, 2017Works involve the construction of a new single-storey extension to the existing bedrooms (34) in 8 blocks, provision of new single storey bedroom wing...
Where the old meets the new at Castleknock College
June 02, 2017New state of the art Sports Hall Gym facility recently completed at Castleknock College. Another superb job carried out by the Nevin Construction team...
Works progressing at the new state of the art R&D Facility at EirGen Pharma.
June 01, 2017A busy day for the Nevin Construction team today, pouring the first floor slab, 390m3 of concrete using two pumps at the new state of the art R&D ...
State Street Bank
April 25, 2017Nevin Construction appointed to carry out the Re-fit Consolidation Project for State Street Bank at Sir. John Rogerson’s Quay, Dublin...
On site at EirGen Pharma
April 07, 2017Eirgen Pharma is a market leader in the development, registration, pharmaceutical, contract manufacturing and supply of high-potency pharmaceutical pr...