News
See what's been happening both on and off site!
Works progressing at the new state of the art R&D Facility at EirGen Pharma.
June 01, 2017A busy day for the Nevin Construction team today, pouring the first floor slab, 390m3 of concrete using two pumps at the new state of the art R&D ...
State Street Bank
April 25, 2017Nevin Construction appointed to carry out the Re-fit Consolidation Project for State Street Bank at Sir. John Rogerson’s Quay, Dublin...
On site at EirGen Pharma
April 07, 2017Eirgen Pharma is a market leader in the development, registration, pharmaceutical, contract manufacturing and supply of high-potency pharmaceutical pr...
Another PTSB project gets underway!
March 28, 2017PTSB BALLINCOLLIG We are delighted to once again be appointed contractor of choice for PTSB. This project will consist of the refurbishme...
Cork Airport
March 24, 2017Restaurant Refurbishment and Upgrade works The Nevin team have now commenced works on the Refurbishment and Alteration to the Ground Floor Cafe and F...
Another Permanent TSB Refurbishment and Fit out completed
September 12, 2016Once again, Nevin Construction were delighted to be appointed as the Contractor of choice, for the refurbishment and fit out of Permanent TSB’s new Br...